Demolition Information
DEMOLITION OVERVIEW
In order to make way for the new Transbay Transit Center at First and Mission streets in downtown San Francisco, the Transbay Joint Powers Authority (TJPA), along with contractor Evans Brothers Inc., must demolish the existing bus ramps and Transbay Terminal facility.
The Transbay Terminal closed on August 6. Bus operations have relocated to the Transbay Temporary Terminal. Demolition activities will last for eight months and will occur in four phases.
Please click on the phases below for more information about work hours, anticipated street closures and duration of each phase.
For more information on the Transbay Temporary Terminal, please visit: temporaryterminal.org
PHASE 1: Aug 14, 2010 – Sep 12, 2010
Because a significant portion of the Temporary Terminal lies below the elevated bus ramp leading to the existing terminal, the northwest corner of the Temporary Terminal will be unfinished when the facility first opens. Demolition of that portion of the ramp will allow for approximately two months of construction in order to finish the Temporary Terminal.
Activity and Closures
- Weekend Closure: Friday, August 13, 2010 – Monday, August 16, 2010 – East Howard St. closure beginning on Saturday, August 14, 2010 through the early morning of Monday, August 16, 2010. Demolition of ramp on Howard St. between Beale & Main & to restore Muni at E. Howard St.
- Activity: Monday, August 16, 2010 – Tuesday, August 24, 2010 – Demolition of ramp at Temporary Terminal site – Monday, August 16, 2010 through Tuesday, August 24, 2010.
- Sidewalk Closure: Wednesday, September 1, 2010 – Friday, September 24, 2010 – A portion of the sidewalk on the south side of Howard, between Beale and Main, will be closed from September 1, 2010 to September 24, 2010. Pedestrians will need to use alternate routes to access the Temporary Terminal.
PHASE 2: Aug 14, 2010 – Oct 29, 2010
Activity and Closures
- Weekday Activity: Monday, August 23, 2010 – Friday, September 3, 2010 – Completion of demolition of bridge bents from Beale Street to Fremont Street.
- Weekday Lane Closure: Tuesday, September 7, 2010 – Friday, September 10, 2010 – Lane closure on Beale Street (between Howard and Mission Streets); demolition prep work under bridge.
- Weekday Lane Closure***: Tuesday, September 7, 2010 – Friday, September 10, 2010 – Lane closure on Howard Street (between Main and Beale Streets); shoring, excavation and removal of bent.
- Weekend Lane Closure: Saturday, September 11, 2010 – Sunday, September 12, 2010 – Lane closure on Fremont and Beale Streets (between Howard and Folsom Streets); demolition of bridge bents.
- Weekday Lane Closure: Monday, September 13, 2010 – Friday, September 17, 2010 – Lane closure on Beale Street (between Howard and Mission) demolition prep work under bridge.
- Weekday Lane Closure***: Monday, September 13, 2010 – Friday, September 17, 2010 – Lane closure on Howard Street (between Main and Beale Streets); removal of bent and foundation; backfill, compaction, and restoring sidewalk.
- Weekend Road Closure: Friday, September 17, 2010 – Monday, September 20, 2010 – Beale Street closed (between Howard and Mission Streets); demolition of Beale Street Bridge.
- Weekend Road Closure: Friday, September 24, 2010 – Monday, September 27, 2010 – Beale Street closed (between Howard and Mission Streets); demolition of Beale Street Bridge.
- Weekend Road Closure: Friday, October 1, 2010 – Monday, October 4, 2010 – Beale Street closed (between Howard and Mission Streets); demolition of Beale Street Bridge.
- Weekend Road Closure: Friday, October 8, 2010 – Monday, October 11, 2010 – Beale Street closed (between Howard and Mission Streets); demolition of Beale Street Bridge.
*** Tentative
PHASE 3: Aug 14, 2010 – Feb 28, 2011
Activity and Closures
- Activity: Monday, August 30, 2010 – Friday, September 3, 2010 – Demolition of Hump.
- Activity: Friday, September 10, 2010 – Friday, October 1, 2010 – Removal of roof of Terminal Building between Fremont St. & First St.
- Night Closure: Friday, October 1, 2010 – Thursday October 7, 2010 – at First St. for the demolition of roof of Terminal Building over First St.
- Activity: Friday, October 1, 2010 – Tuesday, December 28, 2010 – Demolition of Terminal Building between Fremont and First streets.
- Closure: Friday, October 15, 2010 – Monday, October 18, 2010 – First St. closure for the demolition of Terminal Building over First St.
- Closure: Friday, October 22, 2010 – Monday October 25, 2010 – First St. closure for the demolition of Terminal Building Deck over First St.
- Activity: Monday, October 18, 2010 – Friday, November 26, 2010 – Demolition of Terminal Building west of First St.
- Activity: Monday, November 29, 2010 – Wednesday, December 15, 2010 – Demolition of west side of ramp until Howard St.
- Closure: Friday, December 24, 2010 – Monday, December 27, 2010 – West Howard St. Closure for the demolition of ramp over Howard St.
PHASE 4: Aug 14, 2010 – Apr 29, 2011
Activity and Closures
- Activity: Tuesday, December 28, 2010 – Tuesday, January 18, 2011 – Demolition of ramp from Howard to Tehama.
- Activity: Tuesday, January 18, 2011 – Thursday, January 20, 2011 – Tehama St. closure for the demolition of ramp over Tehama St.
- Activity: Thursday, January 20, 2011 – Thursday, February 10, 2011 – Demolition of ramp from Tehama to Clementina.
- Closure: Thursday, February 10, 2011 – Monday, February 14, 2011 – Clementina St. closure for the demolition of ramp over Clementina St.
- Activity: Tuesday, February 15, 2011 – Tuesday, March 22, 2011 – Demolition of ramp from Clementina to Harrison St.
- Activity: Tuesday, March 22, 2011 – Tuesday, April 26, 2011 – Demolition of ramp adjacent to Fremont St. off ramp between First St. & Essex St.
Please be aware that night noise is anticipated whenever weekend street closure work is performed. Please continue to check back for updated schedule information. For urgent site-specific concerns, please call 415.409.TJPA (8572).